Page 1 of 1

Montage Review Calendar

Posted: Fri Feb 21, 2020 8:17 pm
by cobash
Hi!

Has anyone run into a problem when trying to select a date range? The first date box works as expected giving me access to all of the months and days. The second box for the ending range only give me access to the last week. (See Picture Below) I am running Fedora 31, Zoneminder 1.34.2

Thanks!

Image

Re: Montage Review Calendar

Posted: Fri Feb 21, 2020 8:36 pm
by cobash
Forgot to mention I tried this in IE, Chrome, and Firefox. I can manually edit the url and put in a different date and that works fine. Just not the clickable calendar.

Thanks!

Re: Montage Review Calendar

Posted: Fri Feb 21, 2020 11:03 pm
by iconnor
The second calendar won't go before the first one. So if the start calendar is set to Feb 1st, then the second will not go lower than Feb 1st.

Re: Montage Review Calendar

Posted: Mon Feb 24, 2020 6:53 am
by cobash
I understand and that's the way it used to work. But in the picture it is only going back 1 week. I have the first date set to February 1st and the second date is only letting me go back one week from the current date. In my case when I tested it on the 21st and it is only letting me select as far back as the 14th.

Re: Montage Review Calendar

Posted: Mon Feb 24, 2020 9:37 pm
by iconnor
confirmed. Will fix for 1.34.5

Re: Montage Review Calendar

Posted: Wed Feb 26, 2020 8:19 pm
by cobash
Many thanks!!